top button
Flag Notify
    Connect to us
      Site Registration

Site Registration

How many days are required to do the same work with a working of 6 hours per day ?

0 votes
683 views

12 labours construct 120 toys in 8 days working 8 hours per day .
If two them leave the work , then how many days are required to do the same work with a working of 6 hours per day ?

posted Nov 4, 2014 by Balwinder

Share this puzzle
Facebook Share Button Twitter Share Button LinkedIn Share Button

2 Answers (Check Answer ▼)





Similar Puzzles
0 votes

Six men do a piece of work in 10 days with an effort of 6 hours per day. How many extra men are required for doing the work of double strength in 4 days with an effort of 5 hours per day

+1 vote

If A men working A hours a day can do A units of a work in A days, then how many units of work can be completed by B men working B hours per day.

0 votes

3 pumps, working 8 hours a day, can empty a tank in 2 days. How many hours a day must 4 pumps work to empty the tank in 1 day?

+1 vote

If 9 boy working 15/2 hours a day can finish a work in 20 days, then how many days will be taken by 12 boy working 6 hours a day to finish the work, it being given than 3 boy of latter type work as much as 2 boy of he former type in the same.

0 votes

26 operators working 7 hours a day can complete a set of job in 24 days.
In how many day will 21 operators working 8 hours a day do the same set of job?

...