Aadesh alone can do a work in 6 days and Bhavesh alone in 8 days. Aadesh and Bhavesh undertook to do it for Rs. 3200...

+1 vote
353 views

Aadesh alone can do a piece of work in 6 days and Bhavesh alone in 8 days. Aadesh and Bhavesh undertook to do it for Rs. 3200. With the help of Chetan, they completed the work in 3 days.

How much is to be paid to Chetan?

posted Jan 8, 2016 by Anil Chaurasiya

Share this puzzle
Facebook Share Button Twitter Share Button LinkedIn Share Button

2 Answers (Check Answer ▼)





Similar Puzzles
+1 vote

Dhoni can do a piece of work in 80 days. He works at it for 10 days and then Virat alone finishes the work in 42 days.
How many number of days would be taken by the two together to finish the work.

0 votes

Chirag and Bhavesh working together on certain jobs takes 71/2 days to complete it.
Chirag alone takes 8 days less than Bhavesh alone takes.
In how many days Akshay alone can complete the same work, if he is 60% more efficient than Chirag?

0 votes

A can do a piece of work n 7 days of 9 hours each and B alone can do it in 6 days of 7 hours each. How long will they take to do it working together 8 2/5 hours a day?

+1 vote

If 6 men and 8 women can do a piece of work in 10 days and 4 men and 7 women can do it in 12 days, how many days will 4 men and 12 women take to do half of work?

+1 vote

P can do a work in 12 days. Q can do the same work in 8 days and R can do the same in 6 days. Q and R start the work and leave after 2 days. P finishes the remaining work in X days. What is the value of 1.1X?

...