top button
Flag Notify
    Connect to us
      Site Registration

Site Registration

6 men & 8 women can do a work in 10 days, 4 men & 7 women can do it in 12 days, how many days will 4 men and 12 women...

+1 vote
423 views

If 6 men and 8 women can do a piece of work in 10 days and 4 men and 7 women can do it in 12 days, how many days will 4 men and 12 women take to do half of work?

posted May 2, 2018 by anonymous

Share this puzzle
Facebook Share Button Twitter Share Button LinkedIn Share Button

2 Answers (Check Answer ▼)





Similar Puzzles
+1 vote

If 15 men take 21 days of 8 hours each to do a piece of work. How many days of 6 hours each would 21 women take, if 3 women do as much work as 2 men?

0 votes

Nine men can finish a work in 20 days whereas 12 women can finish the same work in 18 days.
If 6 men and 9 women started working together.
After 8 days 3 women left and 2 new men joined the work, the group continued working together till the end of the work.
In how many days they would be able to do the remaining work?

0 votes

Six men do a piece of work in 10 days with an effort of 6 hours per day. How many extra men are required for doing the work of double strength in 4 days with an effort of 5 hours per day

0 votes

10 men and 15 women complete half of the work in 12 days and 6 men and 15 women complete one third of the work in 10 days.
How many days are required to complete the same full work by taking 10 men and 30 women?

0 votes

20 women work on a certain project for 4 days and completes one-tenth of it.
15 men work for the next 'x' days and completes one-fifth of it, if after (4+x) days, 20 women and 15 men work together and completes the remaining work in 12 days, then how many days will 15 men take to complete the whole work?

...