P is able to do a work in 15 days and Q the same work in 10 days. If they work together for 2 days, how much work left?

0 votes
819 views

P is able to do a piece of work in 15 days and Q can do the same work in 10 days. If they can work together for 2 days, what is the fraction of work left?

posted Apr 7, 2017 by anonymous

Share this puzzle
Facebook Share Button Twitter Share Button LinkedIn Share Button

4 Answers

+2 votes

I think it would be 2/3 since:

1 - ((2/15) + (2/10)) = 1 - ((4/30) + (6/30)) = 1 - (10/30) = 1 - 1/3 = 2/3
answer Apr 8, 2017 by anonymous
0 votes

There is a simple trick here to solve problems on work and time faster
First we have to take the LCM of the days both people take to complete a piece of work ie., LCM of 15,10 = 30.
Now this leads to 2 ratios 30/15 = 2 and 30/10 = 3 which represents thier work speed (higher = faster) also 30 represents the total work that needs to be done.

So for this problem both of them are working together for 2 days. So thier speed = 3+2 = 5/day. Therefore total work done after 2 days = 10, which is 1/3rd of the total work done. So the amount work left to be done = 2/3rd.

answer Apr 7, 2017 by Tejas Naik
0 votes

Its given that p does a work in 15 days, it means that P completes (1/15) of the work in each day.
Similarly, it's also given that q does a work in 10 days which means that q completes (1/10) of the work in each day .
Now, p and q are working together for 2 days then:-
1) p completes 2*(1/15) of the work in two days
2) q completes 2*(1/10) of the work in two days
Therefore on adding 2/15 and 2/10 we get 1/3
So one third of the work is completed which implies two third of the work is remaining.
1-1/3=2/3

answer Apr 30, 2017 by Zeeshan Mouzam
0 votes

Work done in 1 day.
1/15+1/10=1/6
Work in 2 days 2*1/6=1/3
Work remained 1-1/3=2/3

answer Apr 30, 2017 by Subhash Gupta



Similar Puzzles
0 votes

P can do a work in 20 days. Q can do the same work in 12 days and R can do the same in 16 days. Q and R start the work and leave after 6 days. P finishes the remaining work in X days. What is the value of X?

+1 vote

P can do a work in 12 days. Q can do the same work in 8 days and R can do the same in 6 days. Q and R start the work and leave after 2 days. P finishes the remaining work in X days. What is the value of 1.1X?

0 votes

P can do a work in 19 days. Q can do the same work in 9.5 days and R can do the same in 28.5 days. Q and R start the work and leave after 3 days. P finishes the remaining work in X days. What is the value of X?

0 votes

B is more efficient than A and they together can complete a work in 18 days.
Had A done 60% of the work and then B, the remaining work, then the work would have been completed in 39 days.
B alone will complete 60% of the same work in how many days?

...