top button
Flag Notify
    Connect to us
      Site Registration

Site Registration

How many more days will be needed to finish the job?

+1 vote
345 views

32 men can finish a job in 32 days, If after 8 days manpower is increased by 28, then how many more days will be needed to finish the job?

posted May 7, 2014 by anonymous

Share this puzzle
Facebook Share Button Twitter Share Button LinkedIn Share Button

1 Answer

0 votes

Answer is 12.8 days.

32 men finish job in 32 days.----------> 1 mean finish job in 32*32 days.
so one men complete per day 1/(32 x 32) of work.

so 32 men in 8 days complete (32 x 8)/(32 x 32) of work ------> 1/4 of work -----> remaining work is 3/4.
now men is increased by 28 so now total men is 60.
now per day compeleted work is ------> 60 x work one men complete per day ------> 60/32 x32= 15 / 256

days need to finish the job = remining work / now per day compeleted work = (3/4)/(15 / 256) = 12.8 days.

answer Jun 20, 2014 by Anuj Agrawal



Similar Puzzles
+1 vote

If 9 boy working 15/2 hours a day can finish a work in 20 days, then how many days will be taken by 12 boy working 6 hours a day to finish the work, it being given than 3 boy of latter type work as much as 2 boy of he former type in the same.

0 votes

A construction company employs 60 men to build a bridge of 500 m in 30 days working 8 hours a day.
If in 24 days they completed 3/5 part of work, then how many more employees should be hired to finish the work in time, working 10 hours a day?

0 votes

B is more efficient than A and they together can complete a work in 18 days.
Had A done 60% of the work and then B, the remaining work, then the work would have been completed in 39 days.
B alone will complete 60% of the same work in how many days?

...