9 men finish one-third work in 10 days. How many additional men required to finish the remaining work in 2 more days?

0 votes
3,131 views
9 men finish one-third work in 10 days. How many additional men required to finish the remaining work in 2 more days?
posted May 22, 2015 by anonymous

Share this puzzle
Facebook Share Button Twitter Share Button LinkedIn Share Button

3 Answers

+2 votes
 
Best answer

9 men do work in 10 days=10*9=90 unit
work left=180 unit
work to be done in one day=180/2=90 unit
additional men=90-9=81

answer May 23, 2015 by Salil Agrawal
0 votes

90 men are required per day

answer May 23, 2015 by anonymous
0 votes

10 * 3 = 30 days;
30 - 10 = 20 days it would take to do the job of nine men.
9 * 20 = 180 man-days;
180/2 = 90 men;
90 - 9 = 81 men additional men required to finish the remaining work in 2 more days.

answer Mar 20, 2016 by Mitrak



Similar Puzzles
0 votes

Six men do a piece of work in 10 days with an effort of 6 hours per day. How many extra men are required for doing the work of double strength in 4 days with an effort of 5 hours per day

0 votes

10 men and 15 women complete half of the work in 12 days and 6 men and 15 women complete one third of the work in 10 days.
How many days are required to complete the same full work by taking 10 men and 30 women?

+1 vote

If 9 boy working 15/2 hours a day can finish a work in 20 days, then how many days will be taken by 12 boy working 6 hours a day to finish the work, it being given than 3 boy of latter type work as much as 2 boy of he former type in the same.

0 votes

A certain number of men can finish a piece of work in 30 days.
If however there were 15 men less it will take 30 days more for the work to be finished.
How many men were there originally?

...