top button
Flag Notify
    Connect to us
      Site Registration

Site Registration

Salil and Aarav can do a piece of work in 45 and 40 days respectively. They began the work together but Salil...........

+1 vote
334 views

Salil and Aarav can do a piece of work in 45 and 40 days respectively. They began the work together but Salil leaves after some days and Aarav finished the remaining work in 23 days.
After how many days did Salil leave?

posted Feb 4, 2016 by Rahul Vaidya

Share this puzzle
Facebook Share Button Twitter Share Button LinkedIn Share Button

2 Answers (Check Answer ▼)





Similar Puzzles
0 votes

Rahul and Maneesh working separately can do a piece of work in 9 days and 12 days respectively. If they work for a day alternately, Rahul beginning, in how many days, the work will be completed?

0 votes

X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last?

0 votes

B alone can complete the work in 45 days.
A is 35% more efficient than B.
If A and B together started the work but after 18 days A and B left.
Then C alone completed the remaining work in 3 days.
If they get Rs. 9750 as wages for the whole work, then what is the share of C in wages for the remaining work?

...