top button
Flag Notify
    Connect to us
      Site Registration

Site Registration

How many days would it take the man who finishes the work if he does the work alone?

+1 vote
351 views

Jatin and Nihal together can complete a work in 10 days. They plan to do the job in a different way. On the first day Jatin works whereas Nihal works for the next 2 days and this pattern is repeated again and again. If they finish the work in 18 days, then in how many days could the man who finishes the work do this work alone ?

posted Jul 24, 2015 by Upma

Share this puzzle
Facebook Share Button Twitter Share Button LinkedIn Share Button

2 Answers

+1 vote

Nihal can do it in 15 days.

If they finish in 18 days, it means that Nihal finishes the job (he works every 2nd and 3rd day of a 3-day shift, 18/3 is last day of 6th shift). During the 18 days, Jatin has worked 6 days and Nihal 12 days. They could also had finished the work if they both worked 10 days. That means that 2 days of Nihal (12-10) equals 4 days of Jatin (10-6).

The 10 days of Jatin could be done by Nihal in only 5 days. Add the original 10 days results in 15 days.

answer Jul 24, 2015 by Jcm
+1 vote

Answer - Jatin alone can complete the work in 30 days and Nihal alone can complete in 15 days.

Explanation can be posted if want.

answer Aug 8, 2015 by anonymous



Similar Puzzles
+1 vote

Dhoni can do a piece of work in 80 days. He works at it for 10 days and then Virat alone finishes the work in 42 days.
How many number of days would be taken by the two together to finish the work.

+1 vote

If 15 men take 21 days of 8 hours each to do a piece of work. How many days of 6 hours each would 21 women take, if 3 women do as much work as 2 men?

0 votes

Ali and Baba need to complete a job. If Ali works alone, he will take 16 more days than if they worked together. Similarly, Baba would take 9 more days than if they worked together. How many days does the job take when Ali and Baba work together?

0 votes

B is more efficient than A and they together can complete a work in 18 days.
Had A done 60% of the work and then B, the remaining work, then the work would have been completed in 39 days.
B alone will complete 60% of the same work in how many days?

...